Motsoaledi outage: City Power cites cable theft, excavation planned
City Power attributes the electricity outage affecting customers in Motsoaledi to multiple incidents of cable theft. In its 11 October update, labelled “Soweto Substation”, the operator says concrete slabs are blocking access to affected cables. It is arranging excavation support for 12 October and sourcing repair materials. No restoration time has been announced.

Status of this incident
Current status unconfirmed
Last known status: confirmed by the source · 11 October, 19:41 SAST: City Power cites cable theft affecting Motsoaledi, with excavation assistance planned for 12 October; no restoration time stated.
Source moment: 11 Oct 2026, 17:41 UTC (19:41 local time)
In 20 seconds
City Power says the Motsoaledi outage was reported on 8 October.
The operator attributes the outage to cable theft; excavation support is planned for 12 October.
Affected customer numbers, the precise onset and restoration time remain unknown.
What is known about the Motsoaledi outage
The outage was reported on Thursday, 8 October, according to City Power. Its first notice acknowledged an unplanned interruption affecting customers in Motsoaledi, within the reporting context of its Lenasia Service Delivery Centre. Individual streets, the number of affected customers and the precise time electricity was lost have not been identified.
The latest statement explicitly names Motsoaledi as the affected area and labels the update Soweto Substation. This identifies the location of the reported work; it does not establish that all of Soweto or Lenasia is without electricity. The available statements also do not connect this interruption to separate outages in Devland or elsewhere.
What the sources tell us, and what they do not
- Reported area
- Motsoaledi; Lenasia Service Delivery Centre
- Operator response
- Excavation assistance planned for 12 October; repair material being sourced
- Affected customers
- Count unknown
- Cause
- Multiple cable-theft incidents, according to City Power
- Restoration estimate
- Not stated
Cable access and repair materials
On 8 October, City Power said operators would investigate after completing their existing task. A 9 October bulletin confirmed operators were still on site investigating the cause. The 11 October statement provides a more specific account: the operator says multiple incidents of cable theft caused the outage. That explanation is attributed to City Power, rather than an independent technical inspection.
The operator says concrete slabs are obstructing access to the affected cables. A section of cable has also been removed from the sleeve pipe beneath the road. City Power is arranging a TLB to assist with excavation on 12 October and sourcing additional material for repairs. This is a work plan, not confirmation that excavation or repairs are complete. The update gives no promised completion time, customer total or restoration estimate, and does not confirm electricity has returned.
Planning essential backup power
The runtime calculator compares essential device demand with battery capacity. The internet backup planner helps plan power for a router and modem, while the backup essentials guide provides a preparation checklist. These tools support household planning; they do not measure local electricity supply or establish a restoration deadline.